Project Summary
A clear overview of the original scope and the requested changes to ensure transparency and professional documentation.
Original Job Description
Remodeling Project: Kitchen Upgrade
Client Information
John & Sarah Miller
Requested Change
Additional Tile Upgrade & Layout Adjustment
Estimated Cost Impact
$1,250.00
Timeline Impact
2 Additional Days
Approval Status
Pending Client Approval
Project History
A complete record of all change orders and project updates for this specific job.
Mar 15, 2026
Approved
Client requested additional tile upgrades to the master bathroom. Change order generated for $1,200 extra material cost and 4 additional labor hours.
Mar 10, 2026
Client requested a layout change for the kitchen island. Estimated timeline extension of 3 days and material cost of $850.
Pending Approval
Mar 05, 2026
Approved
Extra painting requested for the living room. Change order generated for $1,500 extra labor and $200 extra material cost.
Mar 01, 2026
Client requested a plumbing move for the master suite. Change order generated for $1,800 extra labor and $400 extra material cost.
Approved